Report 495 – Job Cost By Phase

Report 495 is found within the jobs list.

 

The primary function of the report is to provide a comparison and overview of estimated, planned, invoiced and actual expenses, grouped by activity and employee.

Parameters

495parm

  • Statement type: Select Cost price or Sales price of hours on the report.
  • Show Phase/Employee group/activity are different groupings available in the report. All can be enabled.
  • Employee group refers to the Employee Price Group.
  • Show Activity must be enabled for Show Employee to work.

 

Column explanation

Example:

495

Job Price (Price quotes)

  • Est Hrs: Total number of hours entered on price quotes (approved or not).
  • Est Price: Total sales price of expenses (hours, materials, purchases, extra) entered on price quotes.
  • Est Cost: Total cost price of expenses (hours, materials, purchases, extra) entered on price quotes.
  • Est Margin = Est Price – Est Cost.

Job Tracking (Expenses and plans)

  • Hrs Reg: Hours entered on the job.
  • Act remaining or ETC: Total number of hours booked on active tasks – Hrs Reg = Total remaining time according to booking.
  • FC Total Hrs: Hrs Reg + Act Remaining = Expected time required to complete task.
  • In progress value: Total cost/sale price (depending on user’s choice) of expenses registered on the job. (hours, materials, purchases).

Billing (Invoices)

  • Hrs Billed: Total number of hours entered on invoices (approved, finalized or not).
  • Billed amount: Total amount of expenses (hours, materials, purchases, extra) billed on invoices.
  • Balance remaining = Billed amount – Est price
  • Realized revenue per hour = Billed amount / Hrs reg
  • Forecastic job margin = Est price or cost (depending on user choice) / FC total hrs