Report 429: Capacity Forecast

Report 429 is found within the Scheduling Module.

Parameters

  • Scope: Parent selection of which resources you would like to show on the report, these could be: ‘All’ , ‘Team’ , ‘Department’ , ‘Company’ or ‘Resource’
  • Scope: Sub selection of which resource
  • Resource booking level: How availability is calculated, ie. based on ideal booking, basic, etc.
  • Date range, start: The report shows 9 weeks from the selected date.
  • Show job details: Show S/F spread out among the individual jobs

 

Column explanation

Example:

Scheduled

Hours booked on jobs that in progress or above, ie. status 1 (green) and above.

Forecasted

Hours booked on quotation jobs, ie. status 0 (yellow).

Available

Number of hours available for booking within the period.

Was this article helpful? Useful Useless 0/0 found this article helpful.